In April 2024, MARTIN AG's boiler service team from Matzingen replaced the front arch and front arch header for the boiler in combustion line 4 for Schwandorf's waste management association ZMS. The old front arch was removed and the new arch installed in the context of the annual overhaul. On site in Schwandorf, the 9 m long front arch header and the piping plates were introduced via the chute shaft due to the new components' size. Owing to our team's fantastic commitment, the work was completed in just under two weeks.
Both the front arch and the front arch header were manufactured by our affiliate MARTIN Caldeiras in Portugal, where the components were cladded in the workshop. This project is a nice example for group-wide collaboration.
We would like to thank ZMS, and in particular all of the staff members of the maintenance team, for the very kind cooperation and superb support. We are looking forward to our next project with ZMS.